Home » Cumulative Achievements

Cumulative Achievements

MDLF cumulative achievements across development sectors up to the end of 2025. Click any sector to explore its achievements.

7Sectors
18Achievement metrics
2025Updated to end of

Water

8km
Water networks rehabilitated
To 2024 0 +8 (FY25)
400m³
Water reservoirs constructed
To 2024 0 +400 (FY25)
2,000
Water pre-paid meters installed
To 2024 0 +2,000 (FY25)
12
Water and wastewater pumps installed
To 2024 0 +12 (FY25)

Environment

2,300kW
Solar energy systems installed
To 2024 0 +2,300 (FY25)

Construction

152,855sqm
Public buildings constructed
To 2024 148,706 +4,149 (FY25)
44km
Retaining walls constructed
To 2024 44
196,805sqm
Parks and public gardens constructed
To 2024 182,526 +14,279* (FY25)

Wastewater

7km
Wastewater networks rehabilitated/constructed
To 2024 0 +7 (FY25)

Electrical

23.8km
Electrical networks rehabilitated
To 2024 22.8 +1 (FY25)
1,647
Electrical pre-paid meters installed
To 2024 1,647
52,155
Lighting units supplied
To 2024 47,453 +4,702 (FY25)

Roads

1,585km
Roads paved, developed, and rehabilitated
To 2024 1,525 +60 (FY25)
470km
Sidewalks/road shoulders constructed
To 2024 470

Solid Waste

6,062
Waste containers supplied
To 2024 0 +6,062 (FY25)
13
Waste collection trucks supplied
To 2024 0 +13 (FY25)
5
Mobile maintenance vehicles supplied for solid waste
To 2024 0 +5 (FY25)
13
Solid waste equipment units supplied
To 2024 0 +13 (FY25)